Lencore Spectra i.Net: Installation and Operations Manual Manuel d'utilisateur Page 40

  • Télécharger
  • Ajouter à mon manuel
  • Imprimer
  • Page
    / 58
  • Table des matières
  • MARQUE LIVRES
  • Noté. / 5. Basé sur avis des utilisateurs
Vue de la page 39
At the last i.Net OP:
Run the last data cable to the IN jack of the last i.Net OP in
the project.
In the last i.Net OP, run a cable from the data OUT to the head end
equipment in the data closet. This will connect to the data IN from
the last i.Net OP on the SmartSwitch.
In the last i.Net OP, click the data terminator into the data
OUT jack. This should only be installed in the last i.Net OP.
section 5
5.16 | data cables
1
a
b
c
36
Vue de la page 39
1 2 ... 35 36 37 38 39 40 41 42 43 44 45 ... 57 58

Commentaires sur ces manuels

Pas de commentaire